CASE FILE / PRODUCT-LAUNCH · ANONYMISED
01 / Event file
02 / Background and challenge
The company placed its annual product launch inside an industry exhibition, with the stand, launch agenda and stream sharing the same floor space.
The organiser allowed two days to build. The launch itself lasted 40 minutes, after which the stand had to remain open for three consecutive days.
03 / Approach
The work was scheduled backwards from the 40-minute launch: screen ratio and camera positions first, then stand circulation and speaker positions.
A control area sat to the left of the stand, with stream cabling routed under the floor. The stand returned to public use within 15 minutes of the launch.
Materials were split into a launch set and a show-open set, with replaceable templates for name plates and screen content.
04 / Implementation
Visuals and run-of-show were locked ten days out, and the build began three days before opening.
A full 40-minute rehearsal covered microphones, teleprompter and stream switching the day before.
Three checkpoints ran on launch day, and dismantling plus asset delivery finished within 48 hours of closing.
05 / Results and evidence
The project ran from contract to dismantling in 18 days, with the launch executed to the minute.
The stand and launch shared one visual system, so no on-site changeover was needed.
The stream matched the stand circulation, and the stand reopened the same day.
06 / Delivery modules
- Visual design
- Stand build
- Launch agenda
- Live streaming
- On-site delivery
- Dismantling